Full Electrics for New Mezzanine Floors at Evans Cycles Warehouse in Crawley
Summary
Main client: Evans Cycles.
Sub-contracted by MI Business Interiors, www.mi-bi.co.uk.
Expansion of Evans Cycles’ bicycle warehouse in Crawley, West Sussex. Full warehouse mezzanine floor installation, with individual office partitioning and fire rated ceilings throughout both floors.
Brief
- Cable containment, steel galvanised cable trays suspended from new mezzanine floor
- LED lighting installed into workshop, offices, stairs and corridors
- Emergency lighting installed into workshop, offices, stairs and corridors
- Fire-rated hoods for all LED lights to comply with building regulations for ceiling fire rating
- Power for offices, desks, floor boxes and sockets fitted
- Power for air-conditioning: single and three-phase
- Power for alarm systems
- Power for fire alarm system
- Power for data/coms room (CAT6)
- Three-phase supply for fork lift chargers
- Single phase supply for lift
- Single-phase lighting fuse box installation (with MCB/ RCBO type fuses)
- Single-phase power fuse box installation (with MCB/ RCBO type fuses)
- Three-phase (mains) fuse box installation
- Testing and NICEIC certification upon completion
Delivery
The project had a fixed completion date of six weeks start to finish and sign-off. The project was completed fully with all objectives met including additional works agreed during the installation, prior to this deadline.
Points of note
- LED lighting installed throughout to minimise running costs with best possible light output levels. These lights also have a very long life expectancy so minimal maintenance costs for duration of the fittings life.
- LED panels installed into new suspended ceiling. These lights had to have fire rated hoods fitted to give the ceiling a full fire rating for building regulations.
- Full emergency lighting system installed to give best possible light levels during power failure.
- Liaison with main project management team to make sure installation was on schedule and budget due to additional works required.
- Liaison with main client, where items to be installed so as they can get best use from them.
- Liaison with main partitioning contractors to make sure all wiring was ahead of schedule for build to not hold up any other trades.
- Liaison with Air conditioning installers for sizing/quantities/positioning of feeds they required; fitting in time for them to do their installation and commissioning.
- Liaison with fire alarm and security alarm installers for positions and amount of feeds they required and installation.